Document No. 545-461
Installation Instructions
July 30, 2008
11. Push firmly on the free end of the Power Open
Processor/Open Processor so that its C-Bus
card edge and M-Bus connector mate with the
C-Bus connector and M-Bus rail (see
Figure 2). You will hear a “click” when the
Power Open Processor/Open Processor is
properly attached to the mounting rail.
c. A Power Open Processor/Ethernet or
Power Open Processor/BACnet, plug one
end of the RJ-45 connector into the
Ethernet jack box, and the other end into
the corresponding (right-hand) Power Open
Processor port labeled EALN.
NOTE: For smoke control applications
over Ethernet:
You must connect to the Ethernet
ALN or BACnet/IP ALN through an
Ethernet switch UL Listed for Fire
Signaling. The panel and the switch
must be installed in the same room.
12. If the Power Open Processor/Open Processor
needs repositioning, pull the metal latch. Pull
the Power Open Processor/Open Processor
forward from the C-Bus connector (see
Figure 2) and repeat Steps 9 through 11.
13. Plug the pre-wired FLN connectors into the
corresponding ports on the left side of the
Power Open Processor/Open Processor. These
ports are labeled FLN 1, FLN 2, and FLN 3 (see
Figure 3). The screws for the connector should
be pointing down.
15. Discard the temporary connector cover.
WARNING: Open Processor/Protocol
2 or Controller Module - Lithium
Battery
Only qualified service personnel or an
authorized Siemens Building
Technologies, Inc. representative can
enable the Open Processor/Protocol 2 or
Controller Module lithium battery.
Improper installation of battery or use of
a different battery may cause an
explosion.
14. Do one of the following. If you are installing:
a. An Open Processor/Protocol 2, plug the
ALN connector into the corresponding port
on the right side labeled BLN + – S (see
Figure 4). The screws for the connector
should be pointing down.
b. A Power Open Processor/Protocol 2, plug
the ALN connector into the corresponding
(right-hand) port labeled BLN. The screws
for the connector should be pointing down.
16. Enable the Power Open Processor/Open
Processor battery by removing the piece of
Mylar that separates the battery from its holder.
17. Switch the MBC/RBC power switch ON.
The installation is now complete.
Siemens Building Technologies, Inc. Page 5 of 6